Renovation – A castle takes shape
‘Castles in and around which no further building work is carried out are doomed to ruin.’
We can only agree with this quote (very loosely based on Kurt Tucholsky). The State of Bavaria has invested a great deal of money in Vöhlin Castle to preserve this valuable historical and cultural heritage.
Particularly during the pandemic years of 2020–2022, we worked closely with the Property Management Department in Augsburg, the State Building Authority in Krumbach, the town of Illertissen and the Facility Management team at Neu-Ulm University of Applied Sciences to carry out modernisation, repair, conversion and renovation work. These works were largely completed in 2022.
Key highlights since 2010
2010: Change of use, in accordance with planning and operational regulations, from an office building (local magistrates’ court) to an events centre
2013: Broadband expansion
2014: Refurbishment of the Castle Bridge
2015: Expansion of car park facilities
2018: Replacement and expansion of the fire alarm system
2022: Completion of façade refurbishment
2023: Restoration of historic softwood parquet flooring
2024: Installation of heat pump technology
2025: Fibre-optic connection
Outlook
2026: West wing – renovation and conversion of the side wing
2027: Castle Park – Creation of parkland and green spaces on the Schlossberg
2028: Climate – Installation of a photovoltaic system on the castle roof
2029: Vöhlinsaal – Creation of a third large seminar room
2030: ‘High Castle’ Hotel – Earth mound structures on the Schlossberg